22 November 2022
Glen Eira Multi-deck car parks (abandoned)
Council decided not to proceed with the proposed multi-deck commuter car park projects in Bentleigh and Elsternwick.
Enter text and select option from the drop-down list
Published on 26 November 2026
We are preparing to reconstruct the road at French Street and the laneway at rear of 58-68 Regent Street, Elsternwick.
This is part of our 2026-27 Capital Works Program and aims to help make streets and laneways safer for traffic and pedestrians.
We are reconstructing the road and the laneway. This will include removing and relaying the bluestones in the existing laneway and upgrading the underground drainage system. French St will also be reconstructed with a new asphalt road pavement and bluestone channels on each side of the road.
Council has appointed A&G Concrete to undertake the works.
Works in French Street are scheduled to begin on Tuesday 1 December 2026 and are expected to take approximately three to four weeks, weather permitting.
Following the Christmas break, works in the laneway are scheduled to begin on Monday 11 January 2027 and are expected to take approximately three weeks, weather permitting.
Works will take place between 7am and 4pm on weekdays. Some Saturday work may also be required between 9am and 1pm. During construction, you may experience some noise and dust. Our contractor will take reasonable steps to minimise these impacts.
The laneway and road will be closed to cars and pedestrians while works are underway. Access to properties from the affected sections may be temporarily unavailable.
If your usual vehicle access is affected, please park on a nearby street or use alternative offstreet parking where available. Please follow all signage and directions from workers when moving through the area.
Work zones and temporary barriers will be installed to keep residents, pedestrians and workers safe.
22 November 2022
Council decided not to proceed with the proposed multi-deck commuter car park projects in Bentleigh and Elsternwick.
07 October 2025
We look after 465 kilometres of roads — making sure they are safe, accessible and meet the needs of our community now and into the future. Read on to learn more about the planned road upgrades during the 2025–2026 financial year.