Carnegie Memorial Swimming Pool timeline and fly through

Come and take a virtual sneak peek inside the proposed redeveloped Carnegie Memorial Swimming Pool.
On This Page

Timeline

When Stage Status
October 2019 to January 2020 Community Consultation Complete
July 2020 to August 2020 Concept Design Complete
October 2020 to May 2021 Detailed Design Complete
April 2021 Melbourne Water planning application Complete
May 2021 Community communications — new Centre detailed design Complete
June 2021 Council adopts detailed design for new Swim Centre Complete
June 2021 Council conducts EOI and commences tender for the head contractor Completed September 2021
October 2021 Heritage appeal, review and statutory process Completed February 2022
May 2022 Heritage Appeal Hearing Completed 17 May 2022
August 2022 Heritage Determination Completed August 2022
Late September 2022 Tender advertised Complete
October 2022 Site preparation and early works Complete
December 2022 Tender awarded Completed December 2022
February 2023 Construction commences On schedule
Late 2024 Centre opens On schedule

Fly through

State-of-the-art design for the new aquatic and leisure facility had been developed as a contemporary facility honouring the past. This modern, sustainable and inclusive facility which upholds a strong sense of nostalgia is developed in consultation with the local community.
  • Carnegie Swim Centre fly through